H
Helen
Hi,
I'm using Project 2002
I have a set of tasks for a person to perform which are all based in a
similar physical location than all the other tasks. When I level the tasks
and the resources, Project splits these tasks between the resources, as it
would if I have made no other reccommendation. I would like to somehow group
these tasks so that they can be performed in any order but by the same
individual resource. My resources are allocated such that I have a 200% man
resource, and each task takes 100% of a man resource.
Thanks
Helen
I'm using Project 2002
I have a set of tasks for a person to perform which are all based in a
similar physical location than all the other tasks. When I level the tasks
and the resources, Project splits these tasks between the resources, as it
would if I have made no other reccommendation. I would like to somehow group
these tasks so that they can be performed in any order but by the same
individual resource. My resources are allocated such that I have a 200% man
resource, and each task takes 100% of a man resource.
Thanks
Helen