G
Gil @ IBM
I need to set up two tasks which can occur in any order, but not at the same
time. Both have the same predecessor task and they also have the same
successor task, it is just that I cannot tell at this point in time the exact
sequence in which the two tasks will occur. For example, let's say you have
to perform two hardware installations in different cities -- you know you
cannot be in both sities at the same time, but you have not yet scheduled the
installations and do not the the exact sequence at this point in time. The
only way I can think of to establish this relationship is to set up 2 task
with one week of work effort and put the assigned resource at 50% so the 2
weeks. Is there a better way?
time. Both have the same predecessor task and they also have the same
successor task, it is just that I cannot tell at this point in time the exact
sequence in which the two tasks will occur. For example, let's say you have
to perform two hardware installations in different cities -- you know you
cannot be in both sities at the same time, but you have not yet scheduled the
installations and do not the the exact sequence at this point in time. The
only way I can think of to establish this relationship is to set up 2 task
with one week of work effort and put the assigned resource at 50% so the 2
weeks. Is there a better way?