S
ssale_uk
Hi,
I've been given a Project Plan which is displaying what I think is an
incorrect Finish Date.
If I enter a new task of 1 day starting on Mon 09/10/06 09:00 the
finish date displays Tue 10/10/06 09:00? Other project plans I have
created in the past show the finish date as Mon 09/10/06 17:00.
I have compared the following in the two project plans and they are the
same:
- Options/Calendar tab and all dates & settings
- Working time (start and finish times)
Is there another setting I have overlooked?
Any help would be appreciated.
Cheers
Steve
I've been given a Project Plan which is displaying what I think is an
incorrect Finish Date.
If I enter a new task of 1 day starting on Mon 09/10/06 09:00 the
finish date displays Tue 10/10/06 09:00? Other project plans I have
created in the past show the finish date as Mon 09/10/06 17:00.
I have compared the following in the two project plans and they are the
same:
- Options/Calendar tab and all dates & settings
- Working time (start and finish times)
Is there another setting I have overlooked?
Any help would be appreciated.
Cheers
Steve