Indenting tasks/Duration issue

T

Tynman

Hello, whenever I indent a group of tasks, the duration for the heading is
calculated incorrectly. For example, I indented two tasks that have a total
duration of 2 days, but the duration on the head task (the task that that the
two tasks are grouped under) show as 14 days. I don't have any precendents
set and I'm not sure what's causing this to happen.
 
F

Felix

Hi Tynman,

I guess the time period between your first and your second task is two weeks
(check the dates). Try the column "work" to show the real work.

Best regards,
Felix
 
T

Tynman

Hi Felix, thanks for the reponse. The time period between the tasks is only
1 day. I've pasted the contents below. The last two are indented into the
first one. Kinda funny, if I paste them into a new project the times show up
correctly. Project is very frusturating...

Task Name Duration Start Work
Finish
Move Servers 14 days Thu 3/16/06 0 hrs Fri 3/17/06
Install DHCP 2 hrs Thu 3/16/06 0 hrs Thu 3/16/06
Move servers 2 days Fri 3/17/06 0 hrs Fri 3/17/06
 
S

Steve House

Go to the menu and look at the Calculation opage under Tools, Options .
Make sure recalculation is set to automatic.
 