I'm looking for the opportunity to show in Ms Project Professional a
warning, when I try to allocate a resource from the enterprise, that
is already allocated...

I'm working with the 2007 infrastructure (MS Proj Pro, PWA, Proj
Server, MOSS).

if I look at the PWA view, I can see the resource availability...

I'm looking for (if it is possible) the opportunity to insert a
warning message (or something similar) in MS Project Professional,
when I try to allocate a Resource that is already allocate (without
have to look at the resource availability in pwa)

thanks so much to everybody

cheers

Vit
 
G

Gérard Ducouret

Hello Vit,
In the Assign Resource dialog of Project Pro, you have the option :Available
to work : x hours on the selected task.
Hope this helps,

Gérard Ducouret
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top