D
Dinh Bao Tuyen
Hi everybody,
How to do this in MS Project:
I'd like to input the following information to Task Usage View: the Actual Work (equivalent to effective effort in my mind), MS Project support this information.
Moreover, I'd like to input the real Work for a specific day
(Example: a developer code the program A in 80man-hour, but his skill is bad, so 80man-hour only equivalent to 60man-hour effective (60= Actual Work). But there is not custom field in Task Usage view, and MS Project doesn't support this function.
Is there another way to do this?
Thank you so much
How to do this in MS Project:
I'd like to input the following information to Task Usage View: the Actual Work (equivalent to effective effort in my mind), MS Project support this information.
Moreover, I'd like to input the real Work for a specific day
(Example: a developer code the program A in 80man-hour, but his skill is bad, so 80man-hour only equivalent to 60man-hour effective (60= Actual Work). But there is not custom field in Task Usage view, and MS Project doesn't support this function.
Is there another way to do this?
Thank you so much