If I have a task-A splitted into two portions A1 & A2, & I want to insert a
new task-B between two portions & link it such that A1 preceeds B as
finish-to-start & A2 succeeds B also as finish-to-start.

The problem is that MS Project 2003 enables me to link B only after A2.

Do anyone have an answer?
Thanks a lot.
 
J

JulieS

Hello Mohammed the Unique,

I'm sorry you cannot create links (dependencies) between the split
portions of a task. A would need to be 2 separate tasks to accomplish
what you are seeking.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


"Mohammed The Unique" <Mohammed The (e-mail address removed)>
wrote in message
news:[email protected]...
 
M

Mohammed The Unique

Hi Julie,

Yeah, I know that solution but I don't like it very much. MS should find a
solution in its next versions of MS Project.

Thanks a lot for paying attention,
Mohammed
 
M

Mike Glen

Hi Mohammed ,

Welcome to this Microsoft Project newsgroup :)

Microsoft do not frequent this newsgroup. So, why not tell Microsoft
yourself? Try this site:
http://office.microsoft.com/en-gb/project/default.aspx. On the left is an
invitation to "Send us your comments".

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top