If I have a task-A splitted into two portions A1 & A2, & I want to insert a
new task-B between two portions & link it such that A1 preceeds B as
finish-to-start & A2 succeeds B also as finish-to-start.
The problem is that MS Project 2003 enables me to link B only after A2.
Do anyone have an answer?