B
bs0341
I am working on a project that is broken up into three phases and I am trying
to keep each specific task on one line but with two start dates and two
differant finish dates. I didn't want to split the task because the duration
of the task becomes off. I've tried adding columns with start date 2 and
finish date 2 but can't get that to work. Any Ideas?
to keep each specific task on one line but with two start dates and two
differant finish dates. I didn't want to split the task because the duration
of the task becomes off. I've tried adding columns with start date 2 and
finish date 2 but can't get that to work. Any Ideas?