A
Amy
I have copied one task in Project A and pasted it as a link in Project B.
My goal is to have any changes of this task made in Project A be reflected
Project B.
The pasted task in Project B does dynamically show any changes in dates and
duration I have made in Project A, but it does not show any changes in
progress, % complete, etc... The task reads as 0% complete in Project B, but
reads 100% complete in Project A. Does anyone know what is causing this, and
if it can be fixed?
I know if I insert the entire Project A into Project B that all changes will
be shown, but in this case, I just want only one task to be shown, not an
entire project.
I would appreciate any help!
My goal is to have any changes of this task made in Project A be reflected
Project B.
The pasted task in Project B does dynamically show any changes in dates and
duration I have made in Project A, but it does not show any changes in
progress, % complete, etc... The task reads as 0% complete in Project B, but
reads 100% complete in Project A. Does anyone know what is causing this, and
if it can be fixed?
I know if I insert the entire Project A into Project B that all changes will
be shown, but in this case, I just want only one task to be shown, not an
entire project.
I would appreciate any help!