Installed Project SP2 - Still having resource baseline problem

S

Sandra

I installed SP2 for Project 2003. I thought that it would fix resource
amounts being correctly rolled up after a Save Baseline for Selected task was
performed. I did check the radio buttons to roll up the totals. But the
Resource Usage display shows that the Work amount is correct but the total
for Baseline Work is not. If I baseline the whole project it works. Our
office is trying to have stagg only baseline the tasks that are affected by
approved change requests instead of baseling the whole project. Did SP2 fix
this and if not when is it going to be fixed?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top