Internal/external resources and Owner questions

G

Guy

In my project schedule I want to distinguish the "Work" to be done (and the
respective budget-cost) between internal and external resources.
How is this possible (with only Project Professional 2003)?

I want also a separate field showing the "Owner" of a task. Is it possible
to select from the resource pool a resource as an owner (in a different
field)?

Thanks.
 
J

John

Guy said:
In my project schedule I want to distinguish the "Work" to be done (and the
respective budget-cost) between internal and external resources.
How is this possible (with only Project Professional 2003)?

I want also a separate field showing the "Owner" of a task. Is it possible
to select from the resource pool a resource as an owner (in a different
field)?

Thanks.

Guy,
It depends a little on where you want the Work and Cost to show up. For
example, do you want to see it in a task view (e.g. Gantt Chart), a
resource view (e.g. Resource Sheet), or in a combination view (e.g.
Resource Usage)? Once that determination is made (and you might want to
read FAQ 51 on our MVP website at:
http://www.mvps.org/project/faqs.htm), then the grouping feature of
Project can be used to show the work and cost of internal versus
external resources separately.

Sure, it is always possible to identify an "owner" for a task. It might
be one of the existing resources assigned to the task or it might just
be a supervisor whose people work on the task. Of course the simplest
approach is to designate a spare text field (e.g. Task Text1) and enter
the owner's name. A value list in a customized field could also be used
to facilitate selection of the owner. If the owner is one of the many
resources assigned to the task, a separate spare field could be
populated with that resource's name but it will require either a formula
or VBA - the latter having the greater flexibility.

John
Project MVP
 
J

Jan De Messemaeker

Hi,

- About cost for internal/external resources
In the resource sheet, i,nsert a column like Flag1 and set it to no/Yes or a
custyom number vcolumn that you set to 1/2 or a text field..
Then look up grouping in the help and group the Resource Usage view on the
iindicator you have entered.

- About the drop-down lists: I don't think so; you can have value lists in
custom text fields but filling them with the resource names is either manual
pr through VBA.

HTH
 
G

Guy

Thanks guys for the info.

Jan De Messemaeker said:
Hi,

- About cost for internal/external resources
In the resource sheet, i,nsert a column like Flag1 and set it to no/Yes or a
custyom number vcolumn that you set to 1/2 or a text field..
Then look up grouping in the help and group the Resource Usage view on the
iindicator you have entered.

- About the drop-down lists: I don't think so; you can have value lists in
custom text fields but filling them with the resource names is either manual
pr through VBA.

HTH
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top