J
jen m
I work at a manufacturing company and I am trying to put together project
timelines based on jobsheets handed in each week and it is my first time
working with microsoft project. The problem I am having is that sometimes the
job sheets are too vague (for example "welding - 10 hrs") and I can't put the
hours towards a certain task as I don't know exactly which task they were
working on. I am afraid that alot of hours will be missing from the timelines
and that the schedule will be off. Is there anything I can do to prevent the
project dates and numbers from being way off?
timelines based on jobsheets handed in each week and it is my first time
working with microsoft project. The problem I am having is that sometimes the
job sheets are too vague (for example "welding - 10 hrs") and I can't put the
hours towards a certain task as I don't know exactly which task they were
working on. I am afraid that alot of hours will be missing from the timelines
and that the schedule will be off. Is there anything I can do to prevent the
project dates and numbers from being way off?