Jump to another timeline location

G

genglehardt

When I am in Task View and I want to jump ahead, say a year or so, is there a
way that I can directly jump to another date without having to scroll across
the timeline until I come to the future date?
 
M

Mike Glen

Hi genglehardt,

Welcome to this Microsoft Project newsgroup :)

Click the goto button on the standard toolbar and enter the date.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 
J

Jim Aksel

I learrn something new everyday. Thanks Mike and Dale.
I do it by pressing F5 and then keying the date
--
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 