In MS Project I created marcos to move tasks to "Today" and "Tomorrow", but I
can't set one to move a task to "yesterday" as that word isn't accepted. How
can I get around this?
 
J

John

MontyN said:
In MS Project I created marcos to move tasks to "Today" and "Tomorrow", but I
can't set one to move a task to "yesterday" as that word isn't accepted. How
can I get around this?

MontyN,
Hey, yesterday already happened - you can't change history :)

However if you really do have a time machine, and Stargate command would
love to hear from you about that, then one way is to use the
DateSubtract Method in VBA. You can look up the full syntax in the VBE
Object Browser.

Hope this helps.
John