R
Robin
Hi,
Is there a way to let the duration of a task automatically change when you
change the task finshish date.
E.g. Task 1 starts on Mon 1st and finishes on the Fri 12th = 10 days
duration. I then chnage the end date to the Fri 19th. By default project puts
a constraint on the end date, keeps the duration at 10 days and moves the
start date to Mon 8th. I would rather it kept Mon 1st and extended the task
to 15 days duration.
Thanks for your time
Is there a way to let the duration of a task automatically change when you
change the task finshish date.
E.g. Task 1 starts on Mon 1st and finishes on the Fri 12th = 10 days
duration. I then chnage the end date to the Fri 19th. By default project puts
a constraint on the end date, keeps the duration at 10 days and moves the
start date to Mon 8th. I would rather it kept Mon 1st and extended the task
to 15 days duration.
Thanks for your time