K
kimg
I have a project of 600 tasks with 20 + resources. When I level, these are
the options set: Manual, Clear Leveling, Date Range, Level by ID, Leveling
can Adjust individual assignments on tasks and leveling can split.
1) I have project A and project B. I need to enter actual work for a task
so I go to the Task Usage Screen. For project A, I enter 8 hours for two
days. Project fills in 0's in the work field for the next day. For project
B, I enter the same 8 hours in on the same days, but Project fills in 8's in
the work fields for the next day. After leveling both projects, project A
finishe on 8/2. Project B finishes up on 7/26. Why the diference in end
days when the same process was applied to each project?
2) I have a task , task C that is 70 hours that has 3 resources working
part time. It should take approx 6 days for each of the resources to finish
up this task. There are two other tasks, task A and task D that the same
resources are assigned to. I level the project. Task A finishes up prior to
Task C. Task C splits 4 times and spans over 30+ days to finish. Task D is
incorporated into one of the splits of Task C, but why would this be when I
am leveling by ID? Shouldn't C finish before D? No dependencies. And, why
so many splits in the C task plus the huge gap in finishing this task?
3) I enter in actual work to the project plan. I level. I make two other
changes, minor changes to actual work, I level. I make no changes. I level.
Project recaculates my end date and all Milestones each time I level by a
few days. When there has not been that much actual work entered, why is
Project reshuffling dates and extending them each time I level. If there are
no changes in tasks 1 - 300, why does Project keep changing the dates of
those tasks everytime I level?
Thanks for the help.
the options set: Manual, Clear Leveling, Date Range, Level by ID, Leveling
can Adjust individual assignments on tasks and leveling can split.
1) I have project A and project B. I need to enter actual work for a task
so I go to the Task Usage Screen. For project A, I enter 8 hours for two
days. Project fills in 0's in the work field for the next day. For project
B, I enter the same 8 hours in on the same days, but Project fills in 8's in
the work fields for the next day. After leveling both projects, project A
finishe on 8/2. Project B finishes up on 7/26. Why the diference in end
days when the same process was applied to each project?
2) I have a task , task C that is 70 hours that has 3 resources working
part time. It should take approx 6 days for each of the resources to finish
up this task. There are two other tasks, task A and task D that the same
resources are assigned to. I level the project. Task A finishes up prior to
Task C. Task C splits 4 times and spans over 30+ days to finish. Task D is
incorporated into one of the splits of Task C, but why would this be when I
am leveling by ID? Shouldn't C finish before D? No dependencies. And, why
so many splits in the C task plus the huge gap in finishing this task?
3) I enter in actual work to the project plan. I level. I make two other
changes, minor changes to actual work, I level. I make no changes. I level.
Project recaculates my end date and all Milestones each time I level by a
few days. When there has not been that much actual work entered, why is
Project reshuffling dates and extending them each time I level. If there are
no changes in tasks 1 - 300, why does Project keep changing the dates of
those tasks everytime I level?
Thanks for the help.