B
Bob
Perhaps this is a simple question:
I have a project with a single task, T1, and resources, R1 and R2. T1 is 10
days work.
If I simply assign R1 and R2 to T1, then both resources work 5 days to
complete the task.
I want to examine what will happen if I have one of the resources work
longer on the task. In order to do this without having to modify the
resource units (since this project could have hundreds of tasks rather than
one), I modify the resource's working time so that R1 now works a 12 hour
day. Project still divides the work evenly between the resources: 5 days
for R1 and 5 days for R2. (For some reason this shows a duration of 6.5
days, which does not seem to corroberate with the scheduling that I see, but
that's not my issue today.)
I'd like to have project schedule the resources so that the time is
distributed so that the task is finished as fast as possible. The only way
that I've found to do that is to:
1. change the duration to 0 days.
2. change the duration to 10 days.
3. modify the work to desired amount - in this case 10 days.
Obviously, this solution doesn't work well for a larger project. Does
anyone have a better way to do this?
Thanks.
I have a project with a single task, T1, and resources, R1 and R2. T1 is 10
days work.
If I simply assign R1 and R2 to T1, then both resources work 5 days to
complete the task.
I want to examine what will happen if I have one of the resources work
longer on the task. In order to do this without having to modify the
resource units (since this project could have hundreds of tasks rather than
one), I modify the resource's working time so that R1 now works a 12 hour
day. Project still divides the work evenly between the resources: 5 days
for R1 and 5 days for R2. (For some reason this shows a duration of 6.5
days, which does not seem to corroberate with the scheduling that I see, but
that's not my issue today.)
I'd like to have project schedule the resources so that the time is
distributed so that the task is finished as fast as possible. The only way
that I've found to do that is to:
1. change the duration to 0 days.
2. change the duration to 10 days.
3. modify the work to desired amount - in this case 10 days.
Obviously, this solution doesn't work well for a larger project. Does
anyone have a better way to do this?
Thanks.