G
Gasperix
Hi, I have the following question:
I am starting to use MS Project on one of my projects and after promising
start I am stuck with the following issue:
From each of my resource I get the information about how much time will he
need for the task, approx. start date of the task and we set a deadline for
the task.
I'd like to put this information in MS Project to plan the project and track
progress, but am having difficulties as MS Project is adjusting start and end
of the task in accordance to the information above, and I am getting a bit
confused.
One possibility would be to calculate the average availability of the
resource from the above data, but this number would change from task to task,
depending on other projects the resource is working on - a lot of redundant
information to be entered. And why when this could be calculated by MSP?
I guess I would actually like to enter the information about start date,
deadline and hours of actual work for each task, assign the resources and MS
Project would have to calculate the availability% of resources by itself.
Can someone point me into the right direction here?
I am starting to use MS Project on one of my projects and after promising
start I am stuck with the following issue:
From each of my resource I get the information about how much time will he
need for the task, approx. start date of the task and we set a deadline for
the task.
I'd like to put this information in MS Project to plan the project and track
progress, but am having difficulties as MS Project is adjusting start and end
of the task in accordance to the information above, and I am getting a bit
confused.
One possibility would be to calculate the average availability of the
resource from the above data, but this number would change from task to task,
depending on other projects the resource is working on - a lot of redundant
information to be entered. And why when this could be calculated by MSP?
I guess I would actually like to enter the information about start date,
deadline and hours of actual work for each task, assign the resources and MS
Project would have to calculate the availability% of resources by itself.
Can someone point me into the right direction here?