i have 71 sub projects. all inserted into a master file. i am finding that
one of the tasks in each sub project blows out instead of being 150mins says
duration at 1515mins. this then makes this resource overallocated by 500-600%
on one day. i level minute to minute & std. and cant get this to change. any
clues?