Levelling - Resources on multiple tasks at the same time

R

ronmcfarlane

I have schedule two tasks

Task a is a support task where I want to put aside 25% of a persons
time to through out the project to assist others.

Task b is a real task. Lets say there is 5 days effot in the task

Lets say they are both starting on the first day of the project
(Monday)

When I add them project assigns 2 hours per day on task a and 5 days of
8 hours on task b both starting on the same day.

There is an overallocation in the first week.
When I level, project moves task b to commence at the end of task a.

I want task b to be allocated 6 hours per day finishing the following
Tuesday.

How can I set it up to do this.
 
J

Jan De Messemaeker

Hi,

To be frank, the answer to your question is "Manually".
Leveling does not change allocation percentages.
One gets by far the best results by allocating Resources 100% to each task
and let leveling sequence them.
From a project management point of view, Theory of Constraints clearly shows
this also is the most effiient way of working.
Hope this helps.
 
J

Joe

Try this:

Set the priority of the support task (task a) to 1000 (no leveling). Set
the allocation of the task for task b to 75%, then level. I think this will
work, try it and see.

Joe
 
J

Jan De Messemaeker

Have you tried it?
It doesn't work when the granumarity is "day by day", sorry.
 
J

Jan De Messemaeker

Sorry, I overlooked the setting at 75%.
This will work because there is no longer an overallocation between teh
tasks.
Sorry for my previous post
 
J

Joe

No Problem Jan,

I know you are an expert in Resource Leveling, so I value your input on
this. Could you explain how the "Look for over allocations on a (“Fill in
the blankâ€) basis" works?

Does this mean that is I choose “Week by Week†that only if a task is
resource is over-allocated by more than 40 hours for the week, it will level?
I am not sure I understand how the "Minute by Minute" option would work.

Thanks,
Joe
 
J

Jan De Messemaeker

Hi,

Your assumption on week by week is exact.
Minute by minute is minute-te by minute - you are aware aren't you that
Project stores every date, every duration, every amount of work in tenths of
minutes?
To complete the thought - after leveling minute by minute no resource should
be "Red" any more.
HTH
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top