R
ronmcfarlane
I have schedule two tasks
Task a is a support task where I want to put aside 25% of a persons
time to through out the project to assist others.
Task b is a real task. Lets say there is 5 days effot in the task
Lets say they are both starting on the first day of the project
(Monday)
When I add them project assigns 2 hours per day on task a and 5 days of
8 hours on task b both starting on the same day.
There is an overallocation in the first week.
When I level, project moves task b to commence at the end of task a.
I want task b to be allocated 6 hours per day finishing the following
Tuesday.
How can I set it up to do this.
Task a is a support task where I want to put aside 25% of a persons
time to through out the project to assist others.
Task b is a real task. Lets say there is 5 days effot in the task
Lets say they are both starting on the first day of the project
(Monday)
When I add them project assigns 2 hours per day on task a and 5 days of
8 hours on task b both starting on the same day.
There is an overallocation in the first week.
When I level, project moves task b to commence at the end of task a.
I want task b to be allocated 6 hours per day finishing the following
Tuesday.
How can I set it up to do this.