L
Laser_razor
Hi,
does somebody can give me a clue how to assign a maximum allowable
material limit to start a new task.
E.g. A Manufacturer is using a workcell where the there are 2 workers,
each 8 hrs on a shift. The total amount of products they can produce
in this workcell are 40 units per day. If they achieved a total of 100
units the task should be closed (end time).
The next task may be easier and they can do now 60 units per day but
the total amount to have the task completed is 234 units..
etc...
Any ideas how to set that up?
I want to monitor units per day processed and man hours required.
thanks
Marcus
does somebody can give me a clue how to assign a maximum allowable
material limit to start a new task.
E.g. A Manufacturer is using a workcell where the there are 2 workers,
each 8 hrs on a shift. The total amount of products they can produce
in this workcell are 40 units per day. If they achieved a total of 100
units the task should be closed (end time).
The next task may be easier and they can do now 60 units per day but
the total amount to have the task completed is 234 units..
etc...
Any ideas how to set that up?
I want to monitor units per day processed and man hours required.
thanks
Marcus