Can anyone help me. I use MP 2003 Enterprise. I have 2 schedules that use
common resources. These project files are not linked. Actual work is being
done in one schedule (Schedule A) and actuals are entered against the tasks.
What I need is for the progress and remaining work to be viewed in Schedule
B. Is there any easy way to show this without adding the resources and work
complete to the second schedule - I do not want the costs to be assigned
against schedule B. The tasks from schedule A are drivers to tasks in
schedule B because of resource availability.
common resources. These project files are not linked. Actual work is being
done in one schedule (Schedule A) and actuals are entered against the tasks.
What I need is for the progress and remaining work to be viewed in Schedule
B. Is there any easy way to show this without adding the resources and work
complete to the second schedule - I do not want the costs to be assigned
against schedule B. The tasks from schedule A are drivers to tasks in
schedule B because of resource availability.