C
Cris
Hi,
I have 18 publications that need to go through the exact same series of 50
tasks from beginning to end, except they have different start dates (usually
staggered by 1 week). I would like to know if there is a way to link the 50
tasks in one publication to the same 50 tasks in the remaining 17
publications, so if I had to change an aspect of a task (e.g. add one more 1
day to the duration) it would change the same aspect for each publication.
Any thoughts would be much appreciated. Thanks you
I have 18 publications that need to go through the exact same series of 50
tasks from beginning to end, except they have different start dates (usually
staggered by 1 week). I would like to know if there is a way to link the 50
tasks in one publication to the same 50 tasks in the remaining 17
publications, so if I had to change an aspect of a task (e.g. add one more 1
day to the duration) it would change the same aspect for each publication.
Any thoughts would be much appreciated. Thanks you