I do not have project server bit would like to try and link various projects
together.
I was trying to create a master project which listed all of the resources in
my team, and then I altered their working time to represent their holidays.
For each project running in my team I created a separate project plan file,
and then linked them all to the master project. I was hoping that, if I
viewed the master project plan, it would give me an holistic view of my
resources - what they will be doing on multiple projects and when they are
off on holiday.
I know project server would be a better solution, but I was hoping that
"Insert/Project..." would give me this flexibility. It doesn't seem to.
What actually happens is that I can view the projects' task lists in the
master plan, but when I view resource usage it shows the usage for the first
project and not the others. furthermore, it ignores the "non working time"
for holidays that I have recorded in the master.
Can anyone help?
Cheers.
together.
I was trying to create a master project which listed all of the resources in
my team, and then I altered their working time to represent their holidays.
For each project running in my team I created a separate project plan file,
and then linked them all to the master project. I was hoping that, if I
viewed the master project plan, it would give me an holistic view of my
resources - what they will be doing on multiple projects and when they are
off on holiday.
I know project server would be a better solution, but I was hoping that
"Insert/Project..." would give me this flexibility. It doesn't seem to.
What actually happens is that I can view the projects' task lists in the
master plan, but when I view resource usage it shows the usage for the first
project and not the others. furthermore, it ignores the "non working time"
for holidays that I have recorded in the master.
Can anyone help?
Cheers.