I want to use a master project with separate sub-projects
for each development release I am managing. Since these
releases overlap, I can add new releases and drop off
releases that are now close.

I also use a common resource pool. All of the sub-
projects will use the same resource pool file. Do I link
the master project file to the resource pool? Which would
make each sub-project file automatically be linked to the
pool file. Or do I need to link each individual sub-
project to the resource pool?
 
C

Cheryl

Hi Joe
You will need to share the resource pool with all the subprojects and the master project
Good Luck
Cheryl
 
J

Jan De Messemaeker

I never link the master to the pool. It is generally empty so there is no
point in linking the emptiness to the pool.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top