Linking Summary tasks

M

Matium

Hi all,

Can anyone tell me why is it bad practice to link summary tasks.

Secondly, my plan increase in size drastically. Any ideas how to get it
to its normal size?
 
J

John

Matium said:
Hi all,

Can anyone tell me why is it bad practice to link summary tasks.

Secondly, my plan increase in size drastically. Any ideas how to get it
to its normal size?

Matium,
Linking summary tasks is probably the number one reason project files
develop circular links. Links to summary lines at best can cause
confusing logic flow and at worst file corruption. Although Project does
allow it, I would avoid it entirely. The only time links on summary
lines MIGHT make sense is for a very high level plan that is used
strictly for planning purposes (i.e. no actively tracked tasks).

If sounds like your file has developed some corruption. Go to our MVP
website at: http://www.mvps.org/project/faqs.htm
and see FAQ 43 = File Bloat? Might be corruption.

Hope this helps.
John
Project MVP
 
J

JackD

John,

This is one of the best responses I've seen on this topic. Nice and concise.
We should put it in the FAQ.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top