linking tasks in Project 2003

J

Jan De Messemaeker

Hi,

There are at least 6 ways to do so, here are a few:

1. Point to the bar of task 4, keep the left mousekey down, draw a line to
the bar of task 22
2. Select a cell of task 4, now hold the ctrl hkey and select a cell of task
22; release the ctrl key and click the link tasks icon on the toolbar
3. In the predecessors column of task 22 type 4
4. Double-click on task 33 to show Task information, in the predecessors
path select 4.

Hope this helps,
 
M

Mike Glen

Hi James,

Welcome to this Microsoft Project newsgroup :)

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #3, at this site: http://tinyurl.com/2xbhc or
this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top