Figen
I have linked various summary tasks to a milestone (I know I should not be
linking summary tasks) and would like to be alerted if the date changes are
made to any of the tasks that may affect the delivery of the milestone.
At the moment if I change any of the dates within these summary tasks,
project automatically updates the milestone without warning, and my
milestones are delivery drops and should not change as easy.
Please help.