Locking dates in Project 2003

V

Veronica

Is there any way to lock dates that have been previously calculated in
Project 2003?
 
J

JulieS

Hello Veronica,

You can certainly copy and paste the dates to a spare date field or
use one of the baseline fields for this, but if you have information
in one of the fields Project uses for calculations (Start, Finish) the
answer is no.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 