A
Asier López
Hello:
Depending on the checks that the members of a project had
activated on PWA, in order to communicate the changes, a
mail is send to them when they make an update and the
project manager accept it. The problem is that the same
happens with administrative projects (like holidays, etc.)
so, there is a way to control (force/unforce) the mails
that are send when updating a project from Project
Professional not depending on the checks the members of
the team conigure in project web access?
Thanks
Depending on the checks that the members of a project had
activated on PWA, in order to communicate the changes, a
mail is send to them when they make an update and the
project manager accept it. The problem is that the same
happens with administrative projects (like holidays, etc.)
so, there is a way to control (force/unforce) the mails
that are send when updating a project from Project
Professional not depending on the checks the members of
the team conigure in project web access?
Thanks