How work Project Server when is updating by multiples users at the same time?
 
M

Marc Soester [MVP]

Hi Mercedes,

it depends on what you wish to update. You can update Risks, Issues -
everthing around the Project Workspace with many users at the same time.

Only one person can update the Project Schedule. In fact this user checkes
out the project, amends it, changes it and check the project back in. During
the time a project is checked out, no other user can change the project.

I hope this helps
 
M

Mercedes Suarez

Thank Marc, but what about a changing status of taks by multiple user,
example: an user is finish the task (100%) other is upgrating to 40%, is
possible to make these at the same time using project web access
 
M

Mercedes Suarez

Yes Thanks

Marc Soester said:
Hi Mercedes,

given that both resources are assigned to the task, both can update the task
at the same time using Project Web Access.
Hope this helps
 