K
KK
My team will have on average 5 dvlp. projects active at any time. One might
be a three days of work, others two weeks, etc. I currently have all
projects loaded into a Master Project with shared resources. I have things
setup so that every resource is allocated 100% of the time to all activities.
I'm separately tracking admin, etc. which would otherwise make them only 80%
avail. Think of their admin time as "just another project". I'll tackle
changing this later.
I'm trying to gauge how to handle multiple projects. If I don't change
anything, new projects are 'likely' to schedule late, meaning after the
existing ones finish (I am not prioritizing now). In reality, what happens
is that some of our customers and their projects could be higher priority
than other work we do but not to a point of saying "finish everything for
high priority customer A 1st" then customer B. I'm thinking of using %
allocation and everything for high priority customer A is stamped with say,
25% allocation, Priority B customer tasks are 10%, 5%, so on & so on. Any
thoughts? Maybe this is why prioritization was created but I'm hesitant
since this will only move higher priority items 1st with "NO" time for any
other acitivites of lesser priority.
be a three days of work, others two weeks, etc. I currently have all
projects loaded into a Master Project with shared resources. I have things
setup so that every resource is allocated 100% of the time to all activities.
I'm separately tracking admin, etc. which would otherwise make them only 80%
avail. Think of their admin time as "just another project". I'll tackle
changing this later.
I'm trying to gauge how to handle multiple projects. If I don't change
anything, new projects are 'likely' to schedule late, meaning after the
existing ones finish (I am not prioritizing now). In reality, what happens
is that some of our customers and their projects could be higher priority
than other work we do but not to a point of saying "finish everything for
high priority customer A 1st" then customer B. I'm thinking of using %
allocation and everything for high priority customer A is stamped with say,
25% allocation, Priority B customer tasks are 10%, 5%, so on & so on. Any
thoughts? Maybe this is why prioritization was created but I'm hesitant
since this will only move higher priority items 1st with "NO" time for any
other acitivites of lesser priority.