G
Ginger
Hi All,
I know that Microsoft creates the critical path based on start and finish
dates, dependencies and 0 slack. When I select the view for Critical path it
is not exactly what I know to be the critical path. Can someone coach and
guide me how I can traverse through my 4000 line plan to manually determine
how microsoft calculated the critical path. Do I start at the bottom of the
plan or at the beginning and what am I looking for?? I know that MSP is
looking at the zero slack but I am also not sure how microsoft project
determines that something has a zero slack.
Thanks, Ginger
P.S. I think this is a really great board for answers.
Thanks, Ginger
I know that Microsoft creates the critical path based on start and finish
dates, dependencies and 0 slack. When I select the view for Critical path it
is not exactly what I know to be the critical path. Can someone coach and
guide me how I can traverse through my 4000 line plan to manually determine
how microsoft calculated the critical path. Do I start at the bottom of the
plan or at the beginning and what am I looking for?? I know that MSP is
looking at the zero slack but I am also not sure how microsoft project
determines that something has a zero slack.
Thanks, Ginger
P.S. I think this is a really great board for answers.
Thanks, Ginger