Abko Wijma
Hello,
I have created a plan that contains a milestone, so duration and work is set
to 0. This milestone is allocated to a team member. Is there a way for the
team member to mark the task as complete from PWA without booking any hours
to it?
Note that we are using the following method for reporting progress on tasks:
'Actual work done and work remaining: Resources report the actual work done
and the work remaining to be done on each task. '
Your feedback is appreciated!
I have created a plan that contains a milestone, so duration and work is set
to 0. This milestone is allocated to a team member. Is there a way for the
team member to mark the task as complete from PWA without booking any hours
to it?
Note that we are using the following method for reporting progress on tasks:
'Actual work done and work remaining: Resources report the actual work done
and the work remaining to be done on each task. '
Your feedback is appreciated!