Marking milestone as complete in PWA

A

Abko Wijma

Hello,

I have created a plan that contains a milestone, so duration and work is set
to 0. This milestone is allocated to a team member. Is there a way for the
team member to mark the task as complete from PWA without booking any hours
to it?

Note that we are using the following method for reporting progress on tasks:
'Actual work done and work remaining: Resources report the actual work done
and the work remaining to be done on each task. '

Your feedback is appreciated!
 
D

Dale Howard [MVP]

Abko --

In the future, please post questions related to Project Server in the
microsoft.public.project.server newsgroup, as this newsgroup is devoted to
the Microsoft Project desktop application only. To answer your question,
no, it is not possible to allow a team member assigned to a milestone task
to update the milestone as complete with assigning at least a token amount
(such as 1 hour) of work to the task. Hope this helps.
 
A

Abko Wijma

Thanks for your prompt reply. I realised to late there is a seperate Project
Server group, sorry for that!
A pity there is no way to mark a milestone as complete other then to
allocate some amount. Thanks for answering my question.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top