gueb
Hi!
If a task end earlier than planned, end milestone is updated.
If a task is longer than planned, end milestone is updated.
But what if the resource didn't work on the task? The milestone should be
update because the project will be late?
I can see with the progress line that the project will be late, but is there
a way to know the estimated end date?
I can increase the task duration knowing the number of days late, but is
there a better way?
http://www.montrealpokersupplies.com/images/other/project1.jpg
If a task end earlier than planned, end milestone is updated.
If a task is longer than planned, end milestone is updated.
But what if the resource didn't work on the task? The milestone should be
update because the project will be late?
I can see with the progress line that the project will be late, but is there
a way to know the estimated end date?
I can increase the task duration knowing the number of days late, but is
there a better way?
http://www.montrealpokersupplies.com/images/other/project1.jpg