No work on a task, end milestone not updated? (but it should)

G

gueb

Hi!

If a task end earlier than planned, end milestone is updated.
If a task is longer than planned, end milestone is updated.

But what if the resource didn't work on the task? The milestone should be
update because the project will be late?

I can see with the progress line that the project will be late, but is there
a way to know the estimated end date?

I can increase the task duration knowing the number of days late, but is
there a better way?

http://www.montrealpokersupplies.com/images/other/project1.jpg
 
J

Jan De Messemaeker

Hi,

Show the Tracking Toolbar
Select the "undone" task
Click the "Reschedle Work" button

The same with more options through Toolls, Tracking, Update Project.
Hope this helps,

Jan De Messemaeker
 
G

gueb

But I have to do this operation every week?

May be I am wrong, but in most projects, almost every week, resources cannot
work as scheduled, so the end date will change every week, so I need to do
this operation once a week?

Thanks guys!!!
 
G

gueb

But I have to do this operation every week?

May be I am wrong, but in most projects, almost every week, resources cannot
work as scheduled, so the end date will change every week, so I need to do
this operation once a week?

Thanks guys!!!
 
G

gueb

Yes I know it's only 2 clicks it is not the problem. I was hoping for an
integrated solution for the problem instead of a 'don't forget the manual
operaton or the end date will be wrong'. :(
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top