Muddypaws
Hi guys
I have created an overall master plan and with 6 different streams:
Service
Training
Operations
Data
Finance
Warranty
Each of the above I have created a single task in the master plan and
then asked the stream leaders to create their individual plans and
then linked their plan to mine. This is so it helps when they ever
change their plan, mine is automatically updated.
There are 6 key milestones, which I have input into my overall plan,
and each of the streams has to ensure that they adhere to the key
milestones in my master plan. My question is can this filer down to
their plan from mine or do thay have to insert the milestones into
their individual plans?
There are also dependencies in between stream plans as well, how can
these be linked?
Sorry these questions maybe a bit basic, but I am new to this and
trying to learn as I go alon
Thanks
I have created an overall master plan and with 6 different streams:
Service
Training
Operations
Data
Finance
Warranty
Each of the above I have created a single task in the master plan and
then asked the stream leaders to create their individual plans and
then linked their plan to mine. This is so it helps when they ever
change their plan, mine is automatically updated.
There are 6 key milestones, which I have input into my overall plan,
and each of the streams has to ensure that they adhere to the key
milestones in my master plan. My question is can this filer down to
their plan from mine or do thay have to insert the milestones into
their individual plans?
There are also dependencies in between stream plans as well, how can
these be linked?
Sorry these questions maybe a bit basic, but I am new to this and
trying to learn as I go alon
Thanks