S
Steve Scott
I have always assumed that a Master Project hrs per day setting would not
overide the hrs per day settings for the calculation of individual tasks in
underlying sub-projects. Having just tested this theory it appears that this
is not the case.
Is there any way I can have a master project with eg a 7hr per day setting
but which will allow legacy sub-projects with 8hr per day settings to be
inserted and calculated as 8hrs not 7hr?