Master Project Calculation of sub-projects with different hrs per

S

Steve Scott

I have always assumed that a Master Project hrs per day setting would not
overide the hrs per day settings for the calculation of individual tasks in
underlying sub-projects. Having just tested this theory it appears that this
is not the case.

Is there any way I can have a master project with eg a 7hr per day setting
but which will allow legacy sub-projects with 8hr per day settings to be
inserted and calculated as 8hrs not 7hr?
 
J

Jan De Messemaeker

Hi Steve,

They will be calculated as the right number of hours but they will SHOW a
number of days based on the master's options.
In your example: 1,14 days.
Days is NOT A CALCULATING UNIT in Proejct, everythiong goes by the minute;
so duration will not change, just the conversion into "days".
HTH
 