G
Gerard
Using Project 2003, I want to consolidate a number of projects into a
master project for overview purposes. Each project has different
calendar/work hours.
As I see it the master calendar dictates at the top level and therefore
effects the “apparent” duration for a task in a subproject if the two
calendars vary? This will obviously not match the original subproject data.
Cheers - Gerard
master project for overview purposes. Each project has different
calendar/work hours.
As I see it the master calendar dictates at the top level and therefore
effects the “apparent” duration for a task in a subproject if the two
calendars vary? This will obviously not match the original subproject data.
Cheers - Gerard