Scottie
I have recently set up a Resource Pool with a number of project files
attached. I have changed the base calendar to 7.5 hrs / day instead of the
default 8 hrs/day. I have done the same for the Resource Pool file.
When I open the Resource Pool and take the option to open a Master File, the
base calendar then changes back to 8 hrs/day. I have tried saving the Master
file and changing the calendar, but the next time I open the Resource Pool it
opens a new Master file.
Please could you advise, if I can change the default calendar when I open
the Master Project option from the Resource Pool?
Thankyou.
attached. I have changed the base calendar to 7.5 hrs / day instead of the
default 8 hrs/day. I have done the same for the Resource Pool file.
When I open the Resource Pool and take the option to open a Master File, the
base calendar then changes back to 8 hrs/day. I have tried saving the Master
file and changing the calendar, but the next time I open the Resource Pool it
opens a new Master file.
Please could you advise, if I can change the default calendar when I open
the Master Project option from the Resource Pool?
Thankyou.