Master project does not have column that names project

J

JolieFate

I have created a master project out of 12 project files but I can't find a
way to lable the individual projects. I want to insert a column that names
each project so I know what I am looking at. Otherwise, it just looks like a
bunch of subtasks.
Thanks so much for you help
jolie
 
J

JulieS

Hi Jolie,

You can add the Project field to show which project file the tasks are
from. The project field is also available in both the Resource Usage
view and Task Usage view.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question