Master Project Filter for Certain Milestones

P

paharam

Hello,

I need to create a filter for a master project, that will display certain
milestones for all of the master's sub projects. Here is an example
structure:

Define (Level 1)
Create Requirements (Level 2)
Requirements Baselined (Level 2)

In the master project file, I only want to display the summary (Define) and
the milestone (Requirements Baselined). Any thoughts on how I can accomplish
this? Thanks.
 
J

JulieS

Hi Paharam,

Try a custom filter (Project > Filtered For> More Filters, New)defined
as:

First row:
Field Name: Outline Level
Test: equals
Value: 1

Second row:
And/Or: Or
Field Name: Milestone
Test: Equals
Value: Yes

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 