P
PattiTechWriter
Currently, we are using Project Pro 03 SP1 (stand alone) to manage a project
that will be delivered in 9 iterations. Iteration 1 (2200+ tasks) is
approaching completion and we have started on a few tasks from I2. (There
will be overlapping of tasks throughout). We have been struggling with
managing the schedule: should we have 9 separate schedules or one large one?
At the rate this project is growing, we could end up with one huge file,
which already takes a while to load. I tested building a master schedule,
using three various projects, but I can't seem to get the predecessors to
link up. What I would like to do is: Assuming I have 3 sub-projects in a
Master Project: Task 24 in I3 (sub-project 3) can't begin until Task 2100 in
I2 (sub-project 2) is completed...or visa versa... Can this be done?
Thanks in advance!
Patti
that will be delivered in 9 iterations. Iteration 1 (2200+ tasks) is
approaching completion and we have started on a few tasks from I2. (There
will be overlapping of tasks throughout). We have been struggling with
managing the schedule: should we have 9 separate schedules or one large one?
At the rate this project is growing, we could end up with one huge file,
which already takes a while to load. I tested building a master schedule,
using three various projects, but I can't seem to get the predecessors to
link up. What I would like to do is: Assuming I have 3 sub-projects in a
Master Project: Task 24 in I3 (sub-project 3) can't begin until Task 2100 in
I2 (sub-project 2) is completed...or visa versa... Can this be done?
Thanks in advance!
Patti