G
gouaux86
I am working on a Project management assignment which entails scheduling and
cost control. As a part of the assignment I built a notional schedule in
project based on a real home imporvement project (with durations, resources
and etc..) I need to calculate the project earned at a particular point in
time. The assignments dictates progression inserting several "trouble
spots". One area I am having problems with is one task is 50% complete, but
100% of the material required has been used.
My question is, how do show all of the material resources budgeted for the
task have been used with the task 50% complete?
cost control. As a part of the assignment I built a notional schedule in
project based on a real home imporvement project (with durations, resources
and etc..) I need to calculate the project earned at a particular point in
time. The assignments dictates progression inserting several "trouble
spots". One area I am having problems with is one task is 50% complete, but
100% of the material required has been used.
My question is, how do show all of the material resources budgeted for the
task have been used with the task 50% complete?