I had 2 activities rolled up and moved them by placing my cursor over it
and
dragged it to another location. The project plan reacted by expanding
another
section that I had closed no where close to the section I was moving
the
content to. Furthermore, it moved one and deleted the other.
:
Just how are you moving them around? I've never encountered Project
deleting tasks on its own. Sometimes it comes as a surprise when one
deletes a summary task forgetting that its children are tied to it and
will
also be deleted at the same time. Is that what's happening with you?
Can you be a little more specific about what you're doing and what you
hope
to achieve?
FYI, Project's theoretical maximum number of tasks in a project is
~1million.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
I have a project plan w/ over 5000 lines. When I begin moving
activities
around, it deletes some of the tasks...and/or puts them in section I
didn't
specify. Has this happened to anyone before? Is there a remedy? Is
there a
recommended max threshold for the number of lines w/in a project
plan?