[Measures].[Work] not what I expected

A

Al Himler

I was putting calulated field in Project Server's Portfolio Manager (Proj
Server 2003) to calculated Planned Utilization. I expected to use the
calculation: [Measures].[Work] \ [Measures].[Availability], but got an
unexpected answer of 200%.

When I created a field to spit back the value in [Measures].[Work] for a
given Month, I found that it was equal to 336 sometimes, 352 sometimes, and
304 sometimes. For the same months the value of [Work] that is displayed is
1 (for 1 hour each month). What is the difference between [Measures].[Work]
and [Work] and how can I use [Work] in a calculated field?

Thanks,

Al
 
M

Mike Glen

You're welcome, Al :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials


Al Himler said:
Will do ...thanks Mike!

Al Himler said:
I was putting calulated field in Project Server's Portfolio Manager (Proj
Server 2003) to calculated Planned Utilization. I expected to use the
calculation: [Measures].[Work] \ [Measures].[Availability], but got an
unexpected answer of 200%.

When I created a field to spit back the value in [Measures].[Work] for a
given Month, I found that it was equal to 336 sometimes, 352 sometimes,
and
304 sometimes. For the same months the value of [Work] that is displayed
is
1 (for 1 hour each month). What is the difference between
[Measures].[Work]
and [Work] and how can I use [Work] in a calculated field?

Thanks,

Al
 