Can you show resources usage on the bottom of a gantt chart. i.e. on a
particular day how many labourers would be needed for a different selection
of tasks.
 
G

Gérard Ducouret

Hi Jedi,

You can do almost that, just a small difference :
Display the Gantt Chart at the upper level, and the *Task* Usage at the
lower level.

Hope this helps,

Gérard Ducouret
 