Is it possible to visualize delays on milestones with constraints?
If I have a baseline plan with a milestone with a "must finish on" or
"finish on and before" constrains with constraint date eg 22.april.2006 - the
milestone "stops" at this date and I get a warning when activities linked to
this milestone have early finish later than 22.april.
Is it possible to visualize the delay for milestones with constraints in the
same way as Project does with milestones without constraints?