I can't adjust the calendar of the project, because that will mess up
all
my
other "normal" tasks. I understand what MS project is doing, and for
all
my
other tasks, it is behaving like I need.
But I have this one task that is a 3 month excercise, always. So, if
the
exercise starts on 1/20, it will always end on 4/20. If it starts on
5/13,
it will end on 8/13. Once the exercise is over, a series of other
tasks
must
then start.
If the tasks leading up to exercise get delayed or finish earlier, the
exercise will start later or earlier. Therefore, I can't just put in
"65
days", because while that might work for a span where the months have
31
and
30 days, it will not work if February is in there, or whatever.
I have created a custom date field as "Date1" that calculates the date
I
need.
dateadd("m",3,[Start])
Is there a way for the finish date to align with the custom "date1"?
If
not, is there another way?
:
So you mean a month and a day?
Just warning you that Project thinks differently than many people do

In Project Start dates are usually at the start of the day and end
dates
are
at the end of the day.
This means a one day task has the same start and finish date. A two
day
task
starts one day and ends the next. A one month task would start on the
first
and end on the 28th, 29th, 30th, or 31st (depending on the year).
You can adjust the amount of time that Project uses when you enter "1
month".
Go to tools menu / options / calendar tab and set the days per month
to
something which you like better.
22 days would probably be just about right for you and is closest to
the
average number of working days per month.
-Jack Dahlgren
message
Well, when I just use 3 months, the task is scheduled about 1.5
weeks
earlier
than possible. That's about 10%, which is enough to make me try to
find a
solution.
The task I'm talking about needs to have the same start and finish
date,
just +3 months, 1/20 - 4/20.
:
I'd start by not worrying about it.
What is a day or two over three months? a couple of percent?
If you can estimate the rest of the task durations to this level of
accuracy
you are a rare individual.
I actually can think of a possible way to do this using custom
field
formulas and paste links, but it is so kludgy I don't want my name
associated with it.
BTW if it starts on 1/20 and was three months it should end on
3/19.
-Jack Dahlgren
in
message
I a project that takes about 1 year. One of the tasks in this
project
takes
exactly 3 months, not 60 working days, not 12 weeks.
The task has predecessors, so the start date may move freely.
So, how do I force Project to correctly calcuate 3 months: Start
1/20,
end
4/20?