W
Wael El Shennawy
I am a new user to MS Project 2000. In one of my project, I encountered the
following cases: 1) one task was done with zero cost. 2) Task started earlier
than scheduled.
in EV reports MSP 2000 ignored the my actual cost entry (zero)for the task
in case (1)and showed the baseline budget of this task and in case (2)
ignored the actual cost to-date I entred for the task started earlier.
following cases: 1) one task was done with zero cost. 2) Task started earlier
than scheduled.
in EV reports MSP 2000 ignored the my actual cost entry (zero)for the task
in case (1)and showed the baseline budget of this task and in case (2)
ignored the actual cost to-date I entred for the task started earlier.