MS Project 2007 - Entering start / finish "hours"

M

milahn01

Can someone give me a suggestion on "how" to show "hours" only in the start
and finish columns instead of a date?
 
D

Dale Howard [MVP]

milahn01 --

You can't. The Start and Finish columns show dates. If you want to see
Work hours, click View - Table - Work. Hope this helps.
 
S

Steve House

Hours starting from what point? Do you mean hours into the project from its
beginning? Can't do that.

If you want time-of-day only instead of date or date/time, go to the tools
menu, option settings, view tab, and select a date format that shows what
you need. Seems really awkward to me but to each his own. A schedule is
supposed to tell the resources where they need to be when in order to do
what.
 